CASE STUDY: Hilton Garden Inn – Soil Stabilization

  • Saved $125,000 overall
  • Utilized standard construction and piping methods
  • Shortened job by 10 days

Hilton Garden Inn Saves Time and Money for a Stronger Foundation

Engineering a better solution

When engineers and contractors explore Soil Stabilization from the start of a job, savings of both time and money can increase dramatically.

The Problem

Engineers were faced with solving foundation issues caused by improperly placed fill material with high moisture content that had been placed atop 3′ of buried organic material, reaching depths of up to 18′. This combination made standard foundation construction impossible, prompting engineers to explore alternate solutions.

The Proposed Approach

Caissons were originally specified to support the foundation, reaching into the stable subgrade below. This support system would require a non-conventional underground piping & construction process; a method that is known to cause major delays in construction and unexpected costs in maintenance.

The Rock Solid Solution

Rock Solid value-engineered a Soil Stabilization process to re-use existing material and avoid non-conventional construction methods, saving money and time.

  1. Remove & Stockpiled Along Perimeter for Re-Use
  2. Removed/Hauled Away (No Re-Use Value)
  3. 12″ SM Fill-ins Were Layered Using The Unstable Soil with Additives Until It Leveled With Grade

Rock Solid Results

money-saved

Saved $125,000 overall

truck-load-savings

Utilized standard construction and piping methods

time-savings-icon

Shortened job by 10 days